Test Planning
- 285 installs
- 55 repo stars
- Updated June 10, 2026
- petrkindlmann/qa-skills
Helps with testing & qa tasks.
About
test-planning is a Claude Code skill for testing & qa. It helps solo builders move faster with AI-assisted development.
- test-planning
- Testing & QA
- AI-coding skill
Test Planning by the numbers
- 285 all-time installs (skills.sh)
- +61 installs in the week ending Aug 4, 2026 (Skillselion tracking)
- Ranked #721 of 2,153 Testing & QA skills by installs in the Skillselion catalog
- Data as of Aug 5, 2026 (Skillselion catalog sync)
npx skills add https://github.com/petrkindlmann/qa-skills --skill test-planningAdd your badge
Show developers this skill is listed on Skillselion. Paste this into your README.
| Installs | 285 |
|---|---|
| repo stars | ★ 55 |
| Last updated | June 10, 2026 |
| Repository | petrkindlmann/qa-skills ↗ |
What it does
Helps with testing & qa tasks.
Files
<objective> Create actionable test plans for sprints and releases. A test plan answers four questions: what to test, how deeply, who does it, and when it must be done. The output is a living document that tracks progress, not a bureaucratic artifact filed and forgotten. A plan that schedules 100% of available time fails the moment the first bug is found — buffer and prioritization are what make it survive contact with reality. </objective>
Quick Route
| Situation | Go to |
|---|---|
| Plan a single sprint | Steps 1-6 below, then the 1-page sprint template in references/plan-documents.md |
| Plan a release | Release template in references/plan-documents.md; the go/no-go decision itself belongs to release-readiness |
| Track an in-flight plan / feed results back | references/tracking-formats.md (daily status + retrospective) |
| Decide what to cut when over capacity | Step 4 prioritization matrix |
---
Discovery Questions
Before writing a test plan, gather context. Check .agents/qa-project-context.md first -- if it exists, use it as the foundation and skip questions already answered there.
Scope
- What is the scope? (single sprint, release, hotfix, feature)
- Which features are new vs. changed vs. unchanged?
- Which features are being released for the first time?
- Are there infrastructure or dependency changes (database migrations, API version bumps, third-party provider switches)?
- Is there a requirements document, PRD, or set of user stories to map against?
Time and Resources
- What is the testing window? (days, hours available)
- Who is available for testing? (SDETs, manual testers, developers)
- Are there shared resources that could bottleneck? (staging environments, test accounts, devices)
- Is there a hard deadline that cannot move, or is the release date flexible?
Risk Context
- Which areas changed the most in this cycle?
- What broke in the last release or sprint?
- Are there known fragile areas or tech debt that increase risk?
- For risk-based prioritization methodology, see
risk-based-testing.
Existing Coverage
- What automated tests already exist for the in-scope features?
- What is the current pass rate of the automated suite?
- Are there known gaps in automation that require manual testing?
- When was the last exploratory testing session on these features?
---
Core Principles
1. Coverage-Driven: Map Every Requirement to at Least One Test
A test plan without traceability to requirements is a guess. Every user story, acceptance criterion, or requirement must map to at least one test case. Gaps in this mapping are untested requirements -- the most dangerous kind of risk.
2. Time-Boxed: Plan Fits the Available Window
Testing expands to fill available time if unbounded. Set a time box for each activity and stick to it. When the window is too short, the prioritization matrix determines what gets cut -- not gut feeling.
3. Prioritized: Not Everything Gets Equal Depth
A payment flow change and a tooltip fix do not deserve equal effort. Use the risk x effort matrix to allocate depth: some features get full regression, others a smoke test, some nothing if low-risk and unchanged.
4. Buffered: Leave Room for the Unexpected
Plans that schedule 100% of available time fail when bugs are found. Allocate only 70-80% of the testing window to planned work and explicitly reserve the remaining 20-30% for bug verification, re-testing, and unplanned investigation. If buffer is not a named line in the plan, you do not have one.
5. Visible: The Plan Is a Communication Tool
Developers need to know what gets tested to write testable code. Product managers need coverage visibility to make release decisions. Publish the plan where the team can see it.
6. Entry and Exit Criteria Are First-Class
The most-reused part of any plan is its gate. Make it explicit, not buried: entry = code-complete on staging + existing suite green + test data seeded; exit = every HIGH-risk area covered + no open P0/P1 + zero unexplained GAP rows in the coverage matrix. Everything else is detail around these two checkpoints.
---
Workflow
The six workflow steps each have a fill-in-the-blank scaffold. The decision prose stays here; the copy-paste templates (decomposition, coverage matrix, estimation worksheet, prioritization matrix, allocation table, schedule) live in references/workflow-templates.md.
Step 1: Feature Analysis and Decomposition
Break each in-scope feature into testable units. A "testable unit" is a specific behavior that can be verified with a clear pass/fail outcome. Walk every feature against these scenario categories so none gets skipped:
- Happy path — the primary success flow.
- Validation — required fields empty, format violations, boundary values.
- Error conditions — server 5xx, network timeout, rejected input.
- Edge cases — unicode, oversized payloads, unsupported formats.
- Concurrency / race conditions — two users edit the same record simultaneously, double-submit, retry-after-timeout. These hide the worst data-corruption bugs and are the category most often missed.
- Integration points — behavior across each boundary the feature crosses.
See references/workflow-templates.md for the decomposition template and a worked "User Profile Edit" example that exercises all six categories.
AI decomposition cross-check. When an agent decomposes features, have it immediately map its own scenarios back against the Step 2 coverage matrix. Any requirement with no scenario, or any scenario category above with no entry, is a decomposition gap the agent must surface before estimation — this is how you catch the agent's blind spots, not after CI does.
Step 2: Requirements-to-Test Coverage Mapping
Create a traceability matrix that maps every requirement to its test cases. See references/workflow-templates.md for the coverage matrix template.
Rules for the coverage matrix:
- Every requirement must appear in the matrix (target: 100% mapping)
- "GAP" status triggers a decision: write a test, accept the risk, or defer
- Automated tests get test IDs that link to the actual test file/function
- Manual tests reference the test case document or charter
Step 3: Effort Estimation
Estimate effort for each test type using historical data. If no historical data exists, use the reference estimates below and calibrate after the first sprint.
Estimation reference (per test case):
| Test Type | Write Time | Execute Time | Maintenance (per quarter) |
|---|---|---|---|
| Unit test | 0.5 hr | < 1 sec | 5 min |
| Integration test | 1 hr | 5-30 sec | 15 min |
| E2E test (Playwright/Cypress) | 2-3 hours | 30s-2 min | 30 min |
| Manual test case (write) | 0.25 hr | 5-15 min per execution | 10 min |
| Exploratory session (charter) | 15 min | 1.5 hrs per session | N/A |
| Accessibility review (manual) | 0.5-1 hr per area | included in write | 15 min |
| Visual regression test | 30-60 min | 10-30 sec | 20 min (baseline updates) |
| Performance test (k6 script) | 2-4 hours | 5-30 min per run | 30 min |
| Prompt regression / LLM eval | 30-60 min per case | 30 sec - 2 min (with API cost) | 20 min |
| Setup & test data (per feature) | 0.5-2 hrs | one-time | re-seed per env |
Write Time is authoring only. The "Setup & test data" row is the line planners most often omit — environment, fixtures, and mock configuration routinely run 20-40% of total effort, so budget it as a real line rather than discovering it mid-sprint.
AI authoring trade-off. Using an agent to author tests cuts Write Time by roughly 40-60%, but add a Review Time line of similar size per case — Bolton's "AI productivity paradox" (2026) is that the speed-up evaporates when an agent ships plausible-but-broken tests that pass a casual review and fail in CI. Seeai-test-generationStep 7 for the review checklist andai-qa-reviewfor the smell taxonomy.
Test-smells review. ISTQB's CTAL-AT v2.0 (May 2026) names test smells as a planning concern. Budget a recurring 30-min "test-smells review" per sprint against the taxonomy in ai-qa-review — cheap, and it finds maintenance debt before it compounds.Use the sprint estimation worksheet in references/workflow-templates.md to roll per-case estimates up to a capacity-utilization figure (target: 70-80%, leaving 20-30% buffer).
Step 4: Prioritization Matrix (Risk x Effort)
When the estimated effort exceeds available capacity (it usually does), use the risk x effort matrix to decide what to cut. See references/workflow-templates.md for the full matrix grid.
For each test case, plot it on the matrix using the risk score from risk-based-testing and the effort estimate from Step 3, then consume capacity in priority order: DO FIRST → DO SECOND → DO THIRD → DEFER → SKIP.
Tie-break rule: within HIGH risk, low-effort beats high-effort — a HIGH-risk / low-effort test (DO FIRST) outranks a HIGH-risk / high-effort test (DO THIRD), because it buys the most risk reduction per hour. Medium-risk items defer before you cut any HIGH-risk coverage; low-risk items defer or skip entirely. Never cut buffer to fit more planned work.
Step 5: Resource Allocation
Assign testing work based on skill match and availability.
Allocation principles:
- Automated test writing goes to SDETs or developers with framework experience
- Exploratory testing goes to the person who understands the feature best (often the developer or product manager, not just QA)
- New feature testing benefits from fresh eyes -- assign someone who did not build it
- Critical path testing should not have a single point of failure -- two people should be able to cover it
- Each person's load stays at 70-80% utilization, not 100% — the rest is their buffer
- Buffer is distributed per person, not lumped into one tester's block: every assignee carries their own buffer line so a blocker on one person does not consume everyone's slack
See references/workflow-templates.md for the allocation table format.
Step 6: Schedule with Buffers
Map testing activities to the sprint timeline. Testing should not be back-loaded to the last two days. See references/workflow-templates.md for the 2-week sprint schedule template.
Key scheduling rules:
- Testing starts as soon as features are code-complete, not at sprint end
- Environment setup and test data preparation happen on Day 1, not Day 3
- Bug verification is continuous, not batched
- The last day is for confirmation, not for starting new testing
---
Plan Documents
Full copy-paste plan documents live in references/plan-documents.md:
- Sprint Test Plan (1-Page) — scope, coverage summary, effort budget, entry/exit criteria, plan risks. Keep a sprint plan to one page.
- Release Test Plan — aggregates sprint plans and adds release-specific concerns (full regression, cross-browser, perf benchmark, security scan, smoke test) plus go/no-go criteria. The go/no-go decision itself belongs to
release-readiness. - Feature Coverage Matrix — per-feature scenario list with priority, test type, location, and status.
- Test Estimation Worksheet — new-test development, existing-suite execution, manual testing, and a summary delta vs. available capacity.
---
Tracking Progress During the Sprint
A test plan is useless if nobody checks it after Day 1. Track progress daily, and feed the results back into future planning at sprint end.
- Daily test status — completed, blocked, bugs found, tomorrow's plan, coverage percentage, and buffer consumed. See the format in
references/tracking-formats.md. - Sprint retrospective inputs — estimation accuracy broken out by test type, coverage delta, bug counts by severity, and lessons. See the format in
references/tracking-formats.md; feed these data points into the next sprint's estimates.
---
Anti-Patterns
Planning Without Risk Assessment
Treating every feature with equal depth wastes effort on low-risk areas and under-tests critical paths. Always run the prioritization matrix (Step 4) before allocating effort. For the full risk methodology, see risk-based-testing.
No Buffer for Bug Discovery
Scheduling 100% of available hours for planned activities leaves no time for verification when bugs are found. Reserve 20-30% as buffer and track consumption daily.
Back-Loading Testing to Sprint End
Leaving all testing for the last two days rushes coverage and surfaces bugs too late to fix. Start testing as features become available; continuous testing beats batch testing at sprint end.
Test Plan as Compliance Artifact
A 30-page plan filed and forgotten helps nobody. The plan should be one page for a sprint, actively tracked, and updated daily. If the plan is not changing, nobody is using it.
Estimating Without Historical Data
Effort estimates pulled from thin air are unreliable. Track actual time spent — broken out by test type — and use that data for future estimates. After 2-3 sprints, estimates become reliable.
Ignoring Environment and Data Setup
Environment setup, test data creation, and mock configuration can consume 20-40% of testing effort. Include the "Setup & test data" row from Step 3 in the estimate or the plan will always run over.
Single-Person Coverage on Critical Path
A single tester covering all critical-path work is a failure point. Ensure at least two people can cover critical-path testing.
---
Verification
Open the produced plan and confirm: every in-scope ticket ID from the sprint board appears in the Scope table; the coverage matrix has zero unexplained GAP rows (each GAP carries an accept/defer note); allocated capacity sums to 70-80% with a named buffer line; and the entry/exit criteria checklists are filled, not placeholder. If any of these fails, the plan is not done.
Done When
- [ ] A sprint or release test plan document exists (1-page sprint template or release template) with scope table, coverage summary, effort budget, and entry/exit criteria all filled in — no placeholders
- [ ] Every in-scope feature is decomposed into specific testable scenarios with pass/fail criteria, covering happy path, validation, error, edge, and concurrency categories
- [ ] A requirements-to-test coverage matrix exists with no unexplained GAP entries (every GAP has an accept-risk or defer note)
- [ ] Each scenario is estimated and plotted on the risk x effort matrix, with deferred items explicitly listed
- [ ] Allocated capacity is 70-80% with 20-30% buffer explicitly reserved as a named line
- [ ] Test data requirements, environment details, and resource allocation are documented in the plan
Reference Files (in references/)
- workflow-templates.md — Fill-in scaffolds for the six workflow steps: decomposition template + example, coverage matrix, sprint estimation worksheet, risk×effort matrix grid, allocation table, and 2-week schedule.
- plan-documents.md — Full copy-paste documents: 1-page sprint test plan, release test plan, feature coverage matrix, and estimation worksheet.
- tracking-formats.md — Daily test status format and sprint retrospective inputs format (with per-test-type variance).
Related Skills
- test-strategy -- The broader QA strategy that test plans execute against; strategy defines the approach, plans implement it per sprint.
- risk-based-testing -- Deep methodology for risk assessment that feeds into the prioritization matrix in Step 4.
- release-readiness -- The go/no-go decision that the release test plan's exit criteria feed into; this skill builds the plan, that one makes the ship call.
- qa-metrics -- Metrics like defect escape rate and estimation accuracy that improve future test plans.
- exploratory-testing -- Structured exploratory sessions referenced in the manual testing sections of the plan.
- qa-project-context -- The project context file that provides baseline answers to discovery questions.
Plan Document Templates
Full copy-paste documents for sprint plans, release plans, coverage matrices, and estimation worksheets. SKILL.md describes when to reach for each; this file holds the templates verbatim.
Sprint Test Plan (1-Page)
# Sprint [N] Test Plan
**Sprint dates:** [start] - [end]
**Features in scope:** [list with ticket IDs]
**Test lead:** [name]
**Last updated:** [date]
## Scope
| Feature | Risk | Test Types | Owner | Status |
|---------|------|-----------|-------|--------|
| [name] | HIGH | E2E, Unit, Exploratory | [name] | Not Started |
| [name] | MED | Unit, Manual | [name] | In Progress |
## Coverage Summary
- Requirements mapped: __ / __ (target: 100%)
- Automated coverage: __ / __ test cases
- Manual coverage: __ / __ test cases
- Gaps identified: __ (with justification)
## Effort Budget
- Total available: __ hours
- Allocated: __ hours (target: 70-80% utilization)
- Buffer: __ hours (20-30%)
## Environment & Data
- Staging URL: [url]
- Test accounts: [location/reference]
- Test data setup: [script/manual steps]
## Entry Criteria
- [ ] Features code-complete and deployed to staging
- [ ] Test data seeded
- [ ] Automated suite passing (existing tests)
## Exit Criteria
- [ ] All HIGH-risk features tested
- [ ] No open P0/P1 defects
- [ ] Coverage matrix shows no unaccepted gaps
- [ ] Regression suite green
## Risks to the Plan
| Risk | Mitigation |
|------|-----------|
| Feature X not code-complete by Day 3 | Test Feature Y first, shift X to Week 2 |
| Staging environment unstable | Run E2E locally against dev server |Release Test Plan
A release test plan aggregates sprint test plans and adds release-specific concerns.
# Release [version] Test Plan
**Release date:** [date]
**Release manager:** [name]
**QA lead:** [name]
## Release Contents
| Sprint | Features | Test Status |
|--------|----------|------------|
| Sprint N | [features] | Complete |
| Sprint N+1 | [features] | In Progress |
## Release-Specific Testing
| Activity | Owner | Schedule | Status |
|----------|-------|----------|--------|
| Full regression on release candidate | [name] | Day -3 | Planned |
| Cross-browser verification (Chrome, Firefox, Safari) | [name] | Day -2 | Planned |
| Performance benchmark vs. previous release | [name] | Day -2 | Planned |
| Security scan on release branch | CI | Day -1 | Planned |
| Smoke test on production after deploy | [name] | Day 0 | Planned |
## Go/No-Go Criteria
See `release-readiness` for the full checklist.
- [ ] All sprint exit criteria met
- [ ] No P0/P1 defects open
- [ ] Performance within 10% of previous release
- [ ] Security scan clean
- [ ] Rollback plan testedFeature Coverage Matrix
# Coverage Matrix: [Feature Name]
| ID | Scenario | Priority | Test Type | Test Location | Status |
|----|----------|----------|-----------|---------------|--------|
| S1 | Happy path: user completes flow | P0 | E2E | e2e/tests/feature/happy.spec.ts | Automated |
| S2 | Validation: required fields empty | P0 | Unit | src/feature/__tests__/validate.test.ts | Automated |
| S3 | Error: server returns 500 | P1 | E2E | e2e/tests/feature/errors.spec.ts | Automated |
| S4 | Edge: unicode in text fields | P2 | Manual | -- | Planned |
| S5 | Perf: page loads under 2s | P1 | Perf | perf/feature-load.js | Automated |
| S6 | A11y: keyboard navigation | P1 | Manual | -- | GAP |Test Estimation Worksheet
# Estimation: [Feature/Sprint Name]
## New Test Development
| Test | Type | Complexity | Estimate | Actual | Notes |
|------|------|-----------|----------|--------|-------|
| Checkout E2E | E2E | High | 3h | -- | Multi-step form |
| Discount calc | Unit | Medium | 1h | -- | 8 combinations |
| Payment API | Integration | High | 2h | -- | Mock gateway |
## Existing Test Execution
| Suite | Count | Est. Duration | Flaky? |
|-------|-------|--------------|--------|
| Unit suite | 342 | 45s | No |
| Integration suite | 87 | 3m | 2 flaky |
| E2E regression | 54 | 12m | 5 flaky |
## Manual Testing
| Activity | Sessions | Duration Each | Total |
|----------|----------|--------------|-------|
| Exploratory: new feature | 2 | 60 min | 2h |
| Cross-browser check | 1 | 45 min | 45m |
| Accessibility review | 1 | 30 min | 30m |
## Summary
| Category | Hours |
|----------|-------|
| New test development | __ |
| Manual testing | __ |
| Bug verification (20% buffer) | __ |
| **Total** | **__** |
| Available capacity | __ |
| **Delta** | **__** |Tracking & Retrospective Formats
Copy-paste formats for tracking a plan during the sprint and feeding results back into future planning. SKILL.md explains the cadence; this file holds the formats verbatim.
Daily Test Status Format
Test Status - [Date]
Completed today:
✓ E2E: checkout happy path (TC-201)
✓ Unit: discount stacking (TC-305, TC-306)
Blocked:
✗ Integration: payment API -- staging env down since 2pm
Action: DevOps notified, ETA unknown
Found today:
BUG-789: Discount applies twice on retry (P1, assigned to Dev)
BUG-790: Avatar upload spinner never stops on timeout (P2, backlog)
Tomorrow:
- E2E: checkout error paths (TC-202, TC-203)
- Exploratory: payment flow edge cases (1h session)
Coverage: 14/22 scenarios complete (64%)
Blockers: 1 (staging environment)
Buffer consumed: 2h of 8h (25%)Sprint Retrospective Inputs
After each sprint, feed these data points back into future planning:
Estimation accuracy: Estimated 40h | Actual 46h | Variance +15%
Cause: Bug verification took 6h more than buffered
Actual vs estimated by test type (feeds Step 3 calibration):
Unit: est 4h | actual 4h | +0% (estimate good)
E2E: est 12h | actual 14h | +17% (page objects slower than assumed)
Exploratory: est 6h | actual 6h | +0%
Setup/data: est 2h | actual 6h | +200% (was under-budgeted — raise next sprint)
Coverage: Planned 22 scenarios | Tested 20 | Skipped 2 (low risk, time pressure)
Gap: accessibility review deferred
Bugs: Total 7 | P0: 0 | P1: 2 | P2: 3 | P3: 2 | Escaped: 0
Lessons:
- Buffer was too low for this complexity (increase to 30%)
- Setup/data was the worst miss — give it a real line next sprint
- E2E write time runs high with page objects; bump to 3h/test
- Start testing Day 2 instead of Day 3Workflow Step Templates
Copy-paste scaffolds for each workflow step in SKILL.md. The decision prose (when and why to use each) lives in SKILL.md; this file holds the fill-in-the-blank artifacts.
Step 1: Feature Decomposition
Decomposition template:
Feature: [Feature Name]
Source: [User story / PRD / Ticket ID]
Testable Scenarios:
1. [User action] → [Expected outcome]
2. [User action with edge case input] → [Expected outcome]
3. [Error condition] → [Expected error handling]
4. [Integration point] → [Expected behavior across boundary]
5. [Performance expectation] → [Response time / throughput target]Example -- User profile edit:
Feature: User Profile Edit
Source: PROJ-1234
Testable Scenarios:
1. User updates display name → Name appears updated across all pages
2. User updates email → Verification email sent, old email works until verified
3. User uploads avatar > 5MB → Error message shown, upload rejected
4. User uploads avatar in unsupported format → Error message with supported formats listed
5. User clears required field and saves → Validation error, field highlighted
6. Two users edit same profile simultaneously → Last write wins, no data corruption
7. Profile edit with slow connection → Loading state shown, no duplicate submissionsStep 2: Coverage Mapping
Coverage matrix template:
| Req ID | Requirement Description | Test Type | Test ID(s) | Status |
|----------|----------------------------------|------------|----------------|------------|
| REQ-101 | User can update display name | Automated | TC-201, TC-202 | Covered |
| REQ-102 | Email change requires verification| Automated | TC-210 | Covered |
| REQ-103 | Avatar upload size limit 5MB | Manual | TC-215 | Planned |
| REQ-104 | Profile changes audit logged | None | -- | GAP |Step 3: Effort Estimation
Sprint estimation worksheet:
Sprint Test Plan Estimation:
New automated tests to write:
Unit: ___ tests × 0.5 hrs = ___ hrs
Integration: ___ tests × 1.0 hrs = ___ hrs
E2E: ___ tests × 2.0 hrs = ___ hrs
Manual testing:
Test cases to execute: ___ × 0.25 hrs = ___ hrs
Exploratory sessions: ___ × 1.5 hrs = ___ hrs
Accessibility reviews: ___ × 0.5-1 hr = ___ hrs
Setup & test data: ___ × 0.5-2 hrs = ___ hrs (per feature — do not omit)
Bug verification buffer (20%): ___ hrs
Re-test after fixes buffer (10%): ___ hrs
Total estimated effort: ___ hrs
Available tester hours this sprint: ___ hrs
Capacity utilization: ___% (target: 70-80%)Step 4: Prioritization Matrix (Risk x Effort)
EFFORT
Low Medium High
(< 1 hr) (1-4 hrs) (> 4 hrs)
+---------------+---------------+---------------+
High | DO FIRST | DO SECOND | DO THIRD |
(CRIT/HIGH | Quick wins | Core coverage | Invest if |
risk score) | on critical | for critical | time allows |
| features | features | |
R +---------------+---------------+---------------+
I Medium | DO SECOND | DO THIRD | DEFER |
S (MED risk | Quick wins | If capacity | Move to next |
K score) | on moderate | allows | sprint |
| features | | |
+---------------+---------------+---------------+
Low | DO IF TIME | DEFER | SKIP |
(LOW risk | Minimal | Not worth | Automate |
score) | effort, why | the effort | later or |
| not | this sprint | never |
+---------------+---------------+---------------+Step 5: Resource Allocation
Allocation table:
| Tester | Available Hours | Assigned Work | Hours | Utilization |
|-----------|----------------|----------------------------------|-------|-------------|
| Alice | 20 | E2E: checkout flow (8h) | 16 | 80% |
| | | Exploratory: payment (4h) | | |
| | | Bug verification buffer (4h) | | |
| Bob | 16 | Unit: discount calc (4h) | 12 | 75% |
| | | Integration: payment API (6h) | | |
| | | Buffer (2h) | | |
| Carol | 12 | Manual: accessibility (4h) | 10 | 83% |
| | | Exploratory: profile edit (4h) | | |
| | | Buffer (2h) | | |Step 6: Schedule with Buffers
Schedule template (2-week sprint):
Week 1:
Day 1-2: Test plan finalized, test data prepared, environments verified
Day 3-4: Automated tests written for features delivered early
Day 5: First round of manual/exploratory testing on available features
Week 2:
Day 1-2: Remaining automated tests written, first round regression
Day 3: Full regression run, bug verification
Day 4: Re-test fixes, exploratory testing on integrated features
Day 5: Final regression, sign-off, release readiness assessment
Buffer allocation:
20% of total hours reserved for unplanned work (bugs, re-tests, blockers)
Bug triage happens daily at standup -- do not wait until Day 5